The Finish Begins

by @ 9:14 am. Filed under Registry Ops

More on the record hall work:

Today 21 tables measuring 48X24 will be ordered for use in the Basement Record Hall. The tables have an oak colored laminate top and steel legs.

Beginning tonight at 6:00PM The Aulson Company will begin removing the tile and carpet from the “old record hall area”.

Next Week:

On Monday the state electrician will cap off the wires that were exposed by the removal of the record book cabinets and will finish installing new outlets on the Elm Street side of the building that will be used to power computers.

On Tuesday a maintenance department employee will finish repairing the holes in the plaster molding where the record book cabinets sat. This repair work requires a bottom fill, finish fill and sanding. ..before it can be painted

Wednesday employees of the trial court will begin painting the exposed walls. The plan is to apply two coats of primer and two finish coats.

Additional…

FYI…I have submitted a work order to the trial court for the heating system in the basement record hall to be checked and repaired.

Leave a Reply

[powered by WordPress.]

Pages:

Recent Posts:

categories:

search blog:

archives:

May 2007
M T W T F S S
« Apr   Jun »
 123456
78910111213
14151617181920
21222324252627
28293031  

Metatasks:

25 queries. 0.395 seconds